Seven sites, three of them planned at around 40,000 homes, sit on England’s draft new towns shortlist. The delivery model behind them may matter as much to builders as the map.
England is preparing to build whole towns again. Seven sites, from the edge of Bristol to the South Bank of Leeds, are on a government shortlist. By our tally of the government’s headline figures, that is around 190,000 homes, three of them at around 40,000 each.
The shortlist was published in March as a draft programme by the Ministry of Housing, Communities and Local Government. As at 10 November 2026, the consultation page still says officials are analysing feedback, so none of the seven is yet confirmed.
Already on paper is the delivery model: public bodies assembling land, infrastructure planned before the houses, town wide design codes and a minimum affordable share. For anyone who builds, supplies or subcontracts, that model matters as much as the map.
Seven sites made the draft shortlist
The list grew out of the New Towns Taskforce report of September 2025, which recommended 12 locations, each designed for at least 10,000 homes. The department then reviewed more than 100 sites, found 13 that met its objectives and proposed seven.
Three are priority interventions. Tempsford in Bedfordshire is proposed as a new standalone settlement of over 40,000 homes around a planned station where East West Rail meets the East Coast Main Line. Crews Hill and Chase Park in Enfield, north London, is put at up to 21,000, and brownfield Leeds South Bank at about 20,000.
Two are mature schemes already under way. Manchester Victoria North, a joint venture between Manchester City Council and Far East Consortium, is set for at least 15,000 homes. Thamesmead in Greenwich is up to 15,000 riverside homes tied to a planned Docklands Light Railway extension.
The last two are described as scalable. Brabazon and the West Innovation Arc in South Gloucestershire, centred on the former Filton Airfield north of Bristol, could reach up to 40,000 homes. Milton Keynes, a postwar new town, is proposed as a renewed town with about 40,000 more.
Six other locations, including Plymouth and South Barking in east London, were judged credible but not prioritised for central resources.
Each town gets a delivery body and a town wide rulebook
The Taskforce noted that no national programme has delivered new communities at the scale needed since the original new town development corporations wound up between 1977 and 1992.
Each confirmed site would be offered, depending on its needs, grant and financial instruments for masterplans, land remediation, land acquisition and enabling infrastructure, help setting up a delivery vehicle, and a New Towns Unit acting as a single front door into government.
The government’s March announcement said some new development corporations will be set up, citing the London Legacy Development Corporation at Stratford.
What is a development corporation?
A public body set up by government to drive a large new settlement or regeneration area. Depending on its powers, it can buy and assemble land, prepare masterplans, act as planning authority and coordinate infrastructure, then sell serviced parcels to builders. England’s postwar new towns were delivered this way, as is Ebbsfleet in Kent today.
Delivery bodies would try to buy land by negotiation first, with compulsory purchase considered where talks fail. The aim is to capture the rise in land value that planning and infrastructure create, and recycle it into affordable housing and community facilities.
A draft New Towns Planning Policy would require each town to have a town wide framework masterplan and a town wide design code, built on ten placemaking principles. Proposals inside a new town area that would clearly harm its planned scale, location or phasing should be refused, and inappropriate Green Belt development within a new town is likely to meet the very special circumstances test.
Affordable homes are set at 40 per cent, with half for social rent
The placemaking principles set a minimum target of 40 per cent affordable housing, at least half of it for social rent. The draft accepts some locations will find this easier than others, depending on how much land is brownfield.
The Taskforce made a supply case for that mix, citing research that build out on large sites with 40 per cent affordable homes runs on average twice as fast as where the share is 10 to 19 per cent. More sales outlets on a site also meant faster building.
Infrastructure comes first, and that sets the pace
Each site’s timetable is tied to its infrastructure. The draft says homes at Tempsford are not expected until wider flood mitigations are in place, and significant housing at Thamesmead waits on site remediation and upgrades to flood and power infrastructure.
Others can move sooner. The department says rapid progress should be possible on a first phase at Brabazon, and delivery at Milton Keynes East, with central and northern Milton Keynes contingent on a local transport solution.
The stated goal is spades in the ground on at least three new towns in this Parliament. The full build will be measured in decades. The strategic environmental assessment assumes 25 years of construction in each location for modelling, while noting that rate is uncertain.
The draft had final locations due in summer 2026. On 1 September, the housing minister told the House of Lords Built Environment Committee that final locations would be announced before the end of 2026, with nearly 3,000 consultation responses to work through.
Builders and suppliers are being offered a long pipeline
The Taskforce’s preferred model is a public body that services land and sells parcels to several builders at once. It argued this gives SME builders a serviced pipeline without much of the planning risk they struggle to carry, and puts multiple housebuilders in competition within one town.
It put numbers on the difference at Brabazon. Under the status quo, it said, building there would likely be limited to up to 80 homes a year, while intervention could unlock more than 700 a year.
Modern methods of construction are encouraged rather than mandated. The Taskforce recommended that delivery bodies actively encourage construction innovation, noting that several modular pioneers had left the market for lack of sustained, predictable demand. Towns of this size, it said, could support new production facilities on site.
Labour is the other side of the ledger. The Taskforce cited analysis for the Construction Industry Training Board estimating that over 200,000 extra construction workers would need to be recruited between 2025 and 2029. That need sits alongside the government’s target of 1.5 million homes this Parliament.
Procurement routes have not been set out; the draft promises delivery detail in the full government response to the Taskforce.
What the final decision settles is less about which fields and brownfield sites get built on, and more about whether government is prepared to act as master developer again at a scale England has not attempted in decades.
For anyone who builds, supplies or subcontracts, that model matters as much as the map.
THE GOOD BUILDER TAKE
The delivery model is the bigger shift. A public body that buys land early, plans water, power and transport first and sells serviced parcels changes who carries risk on a large site. Builders move from holding land and planning risk towards competing on quality, speed and price.
Infrastructure first also means infrastructure dependent. Flood works, rail stations and grid upgrades set the timetable, each with its own budget and approvals.
For builders anywhere, the useful question is not whether around 190,000 homes appear on schedule. It is whether a 40 per cent affordable target, town wide design codes and several builders per site can work together and still beat the conventional route. The first three towns will be the test.
Frequently asked questions
The draft programme published in March 2026 proposes seven locations: Tempsford in Bedfordshire, Crews Hill and Chase Park in Enfield, Leeds South Bank, Manchester Victoria North, Thamesmead in Greenwich, Brabazon and the West Innovation Arc in South Gloucestershire, and Milton Keynes. Six further sites, including Plymouth and South Barking, were judged credible but not taken forward as new towns at this stage.
Each new town must deliver at least 10,000 homes. On the draft programme’s figures, Tempsford is over 40,000, Brabazon up to 40,000, Milton Keynes about 40,000, Crews Hill and Chase Park up to 21,000, Leeds South Bank about 20,000, and Victoria North and Thamesmead around 15,000 each. Added together, those headline figures come to around 190,000 homes over several decades; that is our tally, as the government itself speaks only of hundreds of thousands of homes.
The government’s stated goal is to get spades in the ground on at least three new towns in this Parliament. Final locations were due in summer 2026, but the housing minister told a House of Lords committee on 1 September that they would be announced before the end of 2026. Some sites, such as Tempsford and Thamesmead, depend on flood and other infrastructure work before significant housing can follow.
Each confirmed town will have a delivery vehicle, which may be a new development corporation or an existing joint venture, as at Manchester Victoria North and Thamesmead. The Taskforce’s model has the delivery body assemble land and install infrastructure, then sell serviced parcels to multiple housebuilders, including SMEs. The Taskforce expected housing construction costs to be funded by private housebuilders.
The draft placemaking principles set a minimum target of 40 per cent affordable housing, with at least half of that for social rent. The government says this should be the expectation for all sites, while accepting that some locations will find it easier to meet than others depending on local conditions.
Related articles
- Britain’s Building Problem: 1.5 Million Homes Promised, No Workers to Build Them
- Britain’s New Building Levy Starts on 1 October. The Bill Does Not Arrive Until the Job Is Finished.
- Only 1 in 100 New American Houses Is Modular. The Factory Argument Has Not Gone Away.
Last updated 10 November 2026. Figures current to the New Towns Draft Programme and Strategic Environmental Assessment (MHCLG, March 2026) and ministerial evidence to the House of Lords Built Environment Committee (1 September 2026); consultation outcome not yet published as at 10 November 2026.
General Information Only: The information in this article is general in nature and does not constitute legal, financial, tax or professional advice. It does not take into account your particular circumstances. Laws, regulations and market conditions change, and overseas rules discussed here do not apply in Australia. Independent professional advice is recommended before acting on any information in this article.