$9.1 Billion Moved Through SA’s Planning System. So Where Are Approvals Still Getting Stuck?

South Australia’s annual planning report card shows record development value, a surge in newly titled land and assessment times holding their ground. It also shows where applications keep stalling before an assessor makes a call. South Australia’s planning system approved an estimated $9.1 billion worth of development in the year to 30 June 2026, according […]

Read

Wed 25 Nov 26 8:00:00 AM

tgb-logo-crop

South Australia’s annual planning report card shows record development value, a surge in newly titled land and assessment times holding their ground. It also shows where applications keep stalling before an assessor makes a call.

South Australia’s planning system approved an estimated $9.1 billion worth of development in the year to 30 June 2026, according to the State Planning Commission’s Performance Indicators Scheme annual report for 2025–26, released on 23 November.

That is up from $7.85 billion recorded in the 2024–25 report, a lift of around $1.2 billion in a year. In 2023–24 the figure was $6.2 billion.

The headline number will get the attention. For builders, the more useful parts of the report sit further down: how much new land is coming through, how long consents are taking, and where applications are still losing time.

The report measures the whole planning system, not just housing

The Performance Indicators Scheme has operated since 1 July 2020 and draws its data directly from PlanSA, the state’s single ePlanning platform. Councils, assessment panels and accredited professionals all work through the same system, so the report captures planning, building and land division activity statewide from one data source.

The $9.1 billion covers residential, commercial and industrial work. It is the estimated cost of development that was approved, not money spent on site, so it describes the pipeline ahead rather than work completed.

Part of any rise in approval value can also reflect higher construction costs rather than more projects. The value figure on its own does not separate the two.

More consents were decided and assessment times held steady

Planning authorities determined 32,294 planning consents in 2025–26. The 2024–25 report recorded 31,461. Development applications lodged rose 2.5 per cent, according to the Commission.

The government’s summary of the new report says assessment timeframes held steady on the previous year despite the extra volume. For a benchmark, the 2024–25 report found 90 per cent of planning consent decisions and 93 per cent of building consent decisions were made within statutory timeframes.

Those are statewide averages. Results vary between councils and between assessment pathways, and a Deemed to Satisfy application moves very differently to one that needs public notification or an agency referral.

New titled land jumped for the second year running

The standout figure for anyone building house and land product is the land pipeline. A total of 7,811 new allotments were deposited in 2025–26, and 3,240 land division certificates were issued.

The 2024–25 report recorded 5,671 allotments deposited, and the 2023–24 report 3,271. On those figures, deposited allotments rose by around 38 per cent in a year and have more than doubled across two years.

A deposited plan creates new titles, the point where blocks can be sold and built on. A sustained lift at this stage is an early signal for future house starts, although the timing depends on civil works, service connections and buyer finance.

Deposited allotments rose by around 38 per cent in a year and have more than doubled across two years.

The increase comes as the state works through land and rezoning changes under its Housing Roadmap, released in June 2024. Those include a faster code amendment process, a State Land Division Assessment Panel to take over applications where council timeframes are exceeded, and electronic lodgement of land division dealings.

Land supply is also shaped by market demand and by rezonings made years earlier, so the report’s figures alone do not show how much of the lift is due to any single policy.

Building inspections and occupancy certificates are rising

Building inspections rose to 16,601 in 2025–26, up from 15,295 the year before.

Certificates of Occupancy were issued in substantially greater numbers, which the Commission links to new requirements for houses and townhouses. The 2024–25 report recorded 1,601 certificates across all building classes.

The timing follows the rules. Since 1 October 2024, a Certificate of Occupancy has been required for Class 1a buildings where the building consent application was verified on or after that date. Homes approved under that rule are now reaching handover, which makes 2025–26 the first full financial year where the requirement has flowed through to completed houses in volume.

Under the requirement, a house cannot lawfully be occupied until the certificate is issued, and the PlanSA guidance notes penalties of up to $10,000 may apply. For builders, that makes the paperwork at practical completion part of the handover timeline rather than an afterthought.

Paperwork is where applications still lose time

The report flags room for approvals to move faster, specifically through fewer requests for mandatory documentation at verification and fewer requests for further information during assessment.

Verification and further information: the difference

Verification is the first check after an application is lodged. The relevant authority confirms the application includes the mandatory documents and identifies the correct assessment pathway before assessment begins.

A request for further information comes later, during assessment, when the assessor needs more detail before deciding the application. Both sit with the applicant to resolve.

The pressure has been building. The 2024–25 report counted 16,948 requests for further information, up from 14,175 the year before, an increase of about 20 per cent and faster than the growth in planning decisions. The share of consents verified within the statutory timeframe also slipped, from 86 per cent to 85 per cent.

That same report noted an earlier expert panel recommendation to review Schedule 8 of the planning regulations, which sets out the plans and documents an application has to include, so authorities have enough information to verify it. The review was scheduled for 2025–26, and the department said it could also address the rising number of information requests.

Every verification request or further information request is time that sits with the applicant rather than the assessor. It is why statewide averages can look healthy while individual jobs still drag.

A public data platform is due in the coming weeks

For the first time, the report will be supported by a digital reporting platform that lets anyone explore the data and compare results year on year. The Commission says it is due for release in the coming weeks.

Commission Chair Craig Holden said the platform and additional performance measures would give industry, government and the community greater visibility of how the planning system is performing. The 2024–25 report had flagged a review of the scheme’s indicators in 2025–26 to reflect the online planning tools introduced since it began.

Whether the platform breaks results down by council, by assessment pathway or by accredited professional is not yet known. That level of detail would determine how useful it is to builders comparing where their applications are being assessed.

The Good Builder Take

The $9.1 billion is a pipeline number, and a strong one. But the figures that matter most on a Monday morning are further down the report.

Titled land is up sharply for the second year in a row, which points to more house and land work ahead and more competition for the trades to build it. Occupancy certificates are now a standard step at the end of every new home.

And the report itself identifies incomplete documentation and information requests as the main place time is lost. That part of the approval clock is the one builders and their designers have the most influence over.

Frequently asked questions

How much development did South Australia’s planning system approve in 2025–26?

The State Planning Commission’s Performance Indicators Scheme annual report puts the value of development approved in 2025–26 at an estimated $9.1 billion, up from $7.85 billion in 2024–25. The figure is the estimated cost of approved development across residential, commercial and industrial work, not construction completed.

How many new residential allotments were created in South Australia in 2025–26?

The report records 7,811 new allotments deposited and 3,240 land division certificates issued in 2025–26. The previous two reports recorded 5,671 allotments deposited in 2024–25 and 3,271 in 2023–24.

When did Certificates of Occupancy become required for new houses in South Australia?

A Certificate of Occupancy has been required for Class 1a buildings, which includes houses and townhouses, where the building consent application was verified on or after 1 October 2024. PlanSA guidance says penalties of up to $10,000 may apply for occupying a building without one.

Where are South Australian planning applications losing the most time?

The 2025–26 report identifies requests for mandatory documentation at verification and requests for further information during assessment as areas where approvals could move faster. The 2024–25 report counted 16,948 requests for further information, up from 14,175 the year before.


Related articles

Last updated: 25 November 2026

General information only: This article is general information and does not constitute legal, financial or professional advice. Figures are drawn from published government reports and releases current at the date of publication. Check requirements with PlanSA, your council or a qualified professional before acting.